Data center approvals in Village of Elk Grove Village, IL

Updated October 2026

Data centers are allowed by right where the district permits them, subject to use-specific standards, so the risk sits in the standards and the site plan, not a hearing. Hearings: Plan Commission → Village Board of Trustees.

What the timeline looks like

StepTypical duration or statusWhat drives it
Pre-application10 working days (about 1 month)Staff scheduling and completeness of the concept package
Discretionary approval70 working days (about 3 months)Hearing calendar, notice compliance, opposition, conditions
Site plan40 working days (about 2 months)Review cycles, utility availability letters, stormwater design
Grading permit15 working days (about 1 month)Erosion and sediment control, stormwater permit coverage
Building permit30 working days (about 1 month)Phased permits, fire marshal review, third-party review where available
Certificate of occupancy10 working days (about 1 month)Inspections, commissioning, phased occupancy plan
Whole chain, unappealed175 working days (about 8 months)The steps above run partly in parallel; appeals, utility studies and air permits are not included

working days; estimates from the published process unless noted. Village-published review service levels (5 business days zoning, 10 working days plan review) underpin the site plan and permit figures; the discretionary figure is an estimate from the 2023 Stream docket pace (Plan Commission to Board agenda in about three weeks) with notice lead time and one continuance. Annexation (60 days, veto) and the 90-day appeal window (64 working days) are separate classes.

What slows projects here

What to do about it

Plan this jurisdiction with the register already loaded

PowerPMIS's entitlement gate builds the full requirements register for one live project in two to three weeks, puts every hearing, review and utility step on your critical path, and lists what you can challenge. Fixed fee by project size.

Book a requirements audit

Sources

Timelines are general information drawn from the sources listed, not advice on a specific project. Rules change; confirm current requirements with the authority.