Data center approvals in City of Fort Worth, TX

Updated October 2026

Data centers are a by-right use in the right districts, so the clock is the site plan and permit sequence rather than a vote. Hearings: Zoning Commission → City Council.

What the timeline looks like

StepTypical duration or statusWhat drives it
Pre-application10 working days (about 1 month)Staff scheduling and completeness of the concept package
Discretionary approval70 working days (about 3 months)Hearing calendar, notice compliance, opposition, conditions
Site plan60 working days (about 3 months)Review cycles, utility availability letters, stormwater design
Grading permit30 working days (about 1 month)Erosion and sediment control, stormwater permit coverage
Building permit45 working days (about 2 months)Phased permits, fire marshal review, third-party review where available
Certificate of occupancy15 working days (about 1 month)Inspections, commissioning, phased occupancy plan
Whole chain, unappealed230 working days (about 11 months)The steps above run partly in parallel; appeals, utility studies and air permits are not included

working days; discretionaryApproval converts the City's published '3 months from the monthly application deadline' for a zoning change with an allowance for PD conditions; sitePlan is the platting plus IPRC/CFA sequence (published cycles 21/7 calendar days for plats, 10 business days IPRC first review); gradingPermit covers the drainage study and grading permit (published 10 business days each, two cycles); buildingPermit is two cycles at the published 7-business-day first review; the rest are estimates from the published process

What slows projects here

What to do about it

Plan this jurisdiction with the register already loaded

PowerPMIS's entitlement gate builds the full requirements register for one live project in two to three weeks, puts every hearing, review and utility step on your critical path, and lists what you can challenge. Fixed fee by project size.

Book a requirements audit

Sources

Timelines are general information drawn from the sources listed, not advice on a specific project. Rules change; confirm current requirements with the authority.