Data center approvals in City of Hillsboro, OR

Updated October 2026

Data centers are allowed by right where the district permits them, subject to use-specific standards, so the risk sits in the standards and the site plan, not a hearing. Hearings: Planning and Zoning Hearings Board → City Council.

What the timeline looks like

StepTypical duration or statusWhat drives it
Pre-application15 working days (about 1 month)Staff scheduling and completeness of the concept package
Discretionary approval110 working days (about 5 months)Hearing calendar, notice compliance, opposition, conditions
Site plan40 working days (about 2 months)Review cycles, utility availability letters, stormwater design
Grading permit20 working days (about 1 month)Erosion and sediment control, stormwater permit coverage
Building permit45 working days (about 2 months)Phased permits, fire marshal review, third-party review where available
Certificate of occupancy15 working days (about 1 month)Inspections, commissioning, phased occupancy plan
Whole chain, unappealed245 working days (about 12 months)The steps above run partly in parallel; appeals, utility studies and air permits are not included

working days; discretionaryApproval = Type III Development Review from submittal through the PZHB decision (30-day completeness plus the 120-day ORS 227.178 period, estimate); sitePlan = CWS Site Development Permit (published target 15 + 10 business days) plus City public improvement review, two cycles (estimate); the local appeal (15 days) and LUBA (21 days) windows add about 26 working days before permits; others are estimates from the published process

What slows projects here

What to do about it

Plan this jurisdiction with the register already loaded

PowerPMIS's entitlement gate builds the full requirements register for one live project in two to three weeks, puts every hearing, review and utility step on your critical path, and lists what you can challenge. Fixed fee by project size.

Book a requirements audit

Sources

Timelines are general information drawn from the sources listed, not advice on a specific project. Rules change; confirm current requirements with the authority.