Data center approvals in Loudoun County, Virginia

Updated October 2026

On March 18, 2025, the Loudoun County Board of Supervisors ended by-right data center development countywide. Every new data center now needs a special exception with public hearings before the Planning Commission and the Board. That change sits on top of a Dominion large-load queue running into the 2030s and a statewide generator rule that took effect July 1, 2026.

What the timeline looks like

StepTypical duration or statusWhat drives it
Special exception (zoning)Legislative review with hearings at Planning Commission and Board of Supervisors; applications under review as of Feb 12, 2025 were grandfathered only if more than 500 feet from residential and unchangedLoss of administrative approval; hearing calendars; opposition and conditions
Use-specific standards (Phase 2 of the county's review)About 14 months projected from spring 2025 for standards on data centers, substations, microgrids and generatorsRules can change while an application is pending
Dominion large-load interconnectionRoughly 25 GW of large-load projects with energization dates assigned through 2031; new GS-5 rate class effective Jan 1, 2027 with 14-year contracts and reported collateral of about $1.5M per MWUtility capacity, tariff terms, collateral
Air permit for generator fleet (Virginia DEQ)4 to 6 months synthetic minor; 6 to 12 months state major plus Title V; 1 to 2 years PSD. Applications filed on or after July 1, 2026 must meet Tier 4-equivalent emissionsGenerator count, classification and controls chosen at design
Site plan, phased building permits, inspectionsStandard county cycles; DEQ guidance limits what construction may start before the air permit issuesSequencing of permits against the air permit
Long-lead electrical equipmentPower transformers about 128 weeks; generator step-up units over 160 weeksCannot be ordered safely until tariff, collateral and site control are firm

Durations for air permits are consultant estimates for Virginia; Dominion figures are from the Virginia SCC and Virginia Mercury reporting in 2025 to 2026.

What slows projects here

What to do about it

Plan this jurisdiction with the register already loaded

PowerPMIS's entitlement gate builds the full requirements register for one live project in two to three weeks, puts every hearing, review and utility step on your critical path, and lists what you can challenge. Fixed fee by project size.

Book a requirements audit

Sources

Timelines are general information drawn from the sources listed, not advice on a specific project. Rules change; confirm current requirements with the authority.