Data center approvals in City of New Albany, OH

Updated October 2026

Data centers are allowed by right where the district permits them, subject to use-specific standards, so the risk sits in the standards and the site plan, not a hearing. Hearings: Planning Commission → City Council → Architectural Review Board → Board of Zoning Appeals.

What the timeline looks like

StepTypical duration or statusWhat drives it
Pre-application15 working days (about 1 month)Staff scheduling and completeness of the concept package
Discretionary approval60 working days (about 3 months)Hearing calendar, notice compliance, opposition, conditions
Site plan45 working days (about 2 months)Review cycles, utility availability letters, stormwater design
Grading permit22 working days (about 1 month)Erosion and sediment control, stormwater permit coverage
Building permit22 working days (about 1 month)Phased permits, fire marshal review, third-party review where available
Certificate of occupancy15 working days (about 1 month)Inspections, commissioning, phased occupancy plan
Whole chain, unappealed179 working days (about 9 months)The steps above run partly in parallel; appeals, utility studies and air permits are not included

working days; discretionaryApproval is the final development plan on an already-zoned site (two Planning Commission cycles, estimate; a rezoning, where even possible, is about 150); sitePlan is the engineering construction drawings approval (estimate); gradingPermit is the phased foundation / early-start approval under OBC 105.4 and the thirty-calendar-day plan clock (published, about 22 working days); buildingPermit is the thirty-calendar-day clock under OBC 107.2.1 / ORC 3791.04(E) (published, about 22 working days per review cycle, restarts on resubmittal); certificateOfOccupancy is an estimate

What slows projects here

What to do about it

Plan this jurisdiction with the register already loaded

PowerPMIS's entitlement gate builds the full requirements register for one live project in two to three weeks, puts every hearing, review and utility step on your critical path, and lists what you can challenge. Fixed fee by project size.

Book a requirements audit

Sources

Timelines are general information drawn from the sources listed, not advice on a specific project. Rules change; confirm current requirements with the authority.