Data center approvals in Storey County, NV

Updated October 2026

Data centers are allowed by right where the district permits them, subject to use-specific standards, so the risk sits in the standards and the site plan, not a hearing. Hearings: Planning Commission → Board of County Commissioners.

What the timeline looks like

StepTypical duration or statusWhat drives it
Pre-application15 working days (about 1 month)Staff scheduling and completeness of the concept package
Discretionary approval60 working days (about 3 months)Hearing calendar, notice compliance, opposition, conditions
Site plan20 working days (about 1 month)Review cycles, utility availability letters, stormwater design
Grading permit20 working days (about 1 month)Erosion and sediment control, stormwater permit coverage
Building permit30 working days (about 1 month)Phased permits, fire marshal review, third-party review where available
Certificate of occupancy15 working days (about 1 month)Inspections, commissioning, phased occupancy plan
Whole chain, unappealed160 working days (about 8 months)The steps above run partly in parallel; appeals, utility studies and air permits are not included

working days; discretionaryApproval applies only when a special use permit is triggered (on-site generation plant or structures over 75 ft) and is an estimate against the 65-day hearing deadline; sitePlan is the TRI Architectural Review Committee letter (no county site plan review for I-2; estimate); gradingPermit and buildingPermit are within the county's published 30-business-day plan review ceiling for one cycle; certificateOfOccupancy is an estimate from the CO checklist

What slows projects here

What to do about it

Plan this jurisdiction with the register already loaded

PowerPMIS's entitlement gate builds the full requirements register for one live project in two to three weeks, puts every hearing, review and utility step on your critical path, and lists what you can challenge. Fixed fee by project size.

Book a requirements audit

Sources

Timelines are general information drawn from the sources listed, not advice on a specific project. Rules change; confirm current requirements with the authority.